Winning work does not automatically transfer the tender team's knowledge to the delivery team. A tender response may contain proposed reports, plans, schedules and methods that need to be reconciled with the executed contract before delivery starts.

Preserve the tender baseline

Keep the issued response, attachments, clarifications, addenda and negotiation records in a controlled location. Record the version and date of each. Ask the authorised contract owner to identify which documents and commitments form part of the executed agreement, and which proposals changed or were not adopted.

A documentation coordinator can extract candidate deliverables, but should not decide the legal effect of a tender statement. Mark an uncertain obligation for contract review rather than assuming the most demanding or least demanding interpretation.

Build a deliverable map

For each confirmed deliverable, record its source reference, description, work package, responsible role, required recipient, format, due trigger and review path. Include recurring submissions as separate scheduled occurrences or a clearly defined recurring rule.

Look for dependencies. A final manual may depend on supplier information, installed asset data and commissioning records. The delivery plan should show when those inputs must arrive, rather than recording only the final submission date.

Worked example

A hypothetical maintenance contractor's tender offered monthly performance reports and a mobilisation guide. The executed agreement changes the report format and introduces a client review period for the guide. The delivery register links to the agreed documents and records the revised requirements.

The project administrator asks the report owner to confirm the data source and first reporting period. The mobilisation-guide row identifies who supplies local contacts, who checks the draft and who can issue the final version. The tender's older wording remains in the history but does not silently drive the current plan.

Close the handover between teams

Review the draft map with the tender lead, contract owner and delivery manager. Resolve unclear language and identify any promises requiring resourcing or specialist input. Record decisions and approval of the delivery baseline.

Business Queensland's guidance distinguishes specifications, tender conditions and contract conditions. Use the actual executed agreement and qualified advice where interpretation is needed. The deliverable map is a coordination record: it helps the delivery team see confirmed work, dependencies and dates, while keeping contractual decisions with the person appointed to make them.