A handover dashboard should be a clear view of a reliable register, not a second source of project status. Before choosing colours or charts, decide what each row represents and which decisions the dashboard should support.
Define the denominator
A count of documents is different from a count of required deliverables, work lots or individual assets. Choose the unit and state it beside the measure. If one deliverable requires several files, record whether the dashboard counts the deliverable as a single package or each file separately.
Define status labels with the team. Useful stages might include not received, received, under review, returned for action and accepted by the authorised reviewer. A percentage of files received must not be labelled as percentage of work complete or percentage compliant.
Build three useful views
The first view shows the stage of the required deliverables at a stated reporting time. The second highlights upcoming and overdue actions by owner. The third shows blockers: unclear requirements, unavailable source records or unresolved review comments.
Add the last-updated date and the register version or source link. If data is exported manually, explain that the dashboard is a snapshot. Staff should know where to check current status after the reporting cut-off.
Worked example
A hypothetical electrical package has forty required deliverable rows. Thirty have files linked, but only twenty have an accepted review response. The dashboard shows both “received: 30 of 40” and “accepted by designated reviewer: 20 of 40”, with the definitions visible.
It also shows that five of the outstanding actions are with suppliers and five are awaiting internal review. The project lead can then act on the relevant queue instead of sending a general request for everyone to finish their paperwork.
Test the numbers against real rows
Select several dashboard totals and trace them back to the register. Check how cancelled, superseded and not-applicable items are treated. A not-applicable classification should have an owner-confirmed reason; removing difficult rows from the denominator without explanation makes trends misleading.
Keep early dashboards simple. A short exception table may lead to better decisions than a complicated score. The dashboard reports the recorded evidence state and review route; it cannot itself certify quality, contract completion or readiness for operation.