Factory acceptance test records are easier to use when the reviewer can connect the report to the equipment supplied. For inverter packages, model names alone may be insufficient because several units can share the same model and configuration family. An index should preserve the test record's original scope and connect it to the correct unit or defined group of units.

Define the test-pack identity

Ask the supplier and project technical lead which identifiers govern the package. These may include an inverter serial number, skid reference, transformer identifier or vendor equipment number. Record the identifiers exactly as stated in the source files and keep aliases in separate fields.

List the supplied procedure or test-plan reference, its revision where shown, report number, test date, issuer and equipment references. If a document is described as a type test or routine test instead of a project-specific factory acceptance test, retain that description. Renaming every vendor report FAT does not make the records equivalent.

Keep the complete evidence set together

Preserve report attachments, result sheets, signatures and stated exceptions. Add the relevant review comments and supplier responses as linked records rather than editing them into the original report. Where the final pack requires a signed copy, track that request separately from receipt of an unsigned draft.

An index can identify absent pages, inconsistent identifiers or unreadable scans. It cannot decide whether the test programme, results or exceptions are technically acceptable. Mark those issues for the appointed reviewer and record the actual decision when it is issued.

Hypothetical example

Two inverter skids have similar equipment tags, and a report references only the vendor's internal unit number. The coordinator records the ambiguity and requests a vendor mapping to the project tag. Once the responsible reviewer confirms the mapping, the register links the report to the appropriate unit and retains that confirmation.

Issue a navigable handover set

Arrange the final index by the equipment hierarchy used by the project. Show the source filename, revision, linked equipment and review status. Keep superseded reports in a controlled archive, clearly separated from the issue set without losing their history.

Before release, sample one equipment entry and follow its links to the complete report and its review trail. This is a retrieval check, not a repeat of factory testing. Do not imply that indexed factory records establish site commissioning readiness, warranty eligibility or permission to energise; those matters have their own responsible people and source documents.