The practical question

A machine that is unavailable still generates costs. Downtime includes planned servicing, unexpected repairs, weather interruption, transport delays and waiting for site access. Treating every working day as billable can understate both the rate required and the reserve needed.

A workable approach

Create a downtime register with date, duration, cause, cost, lost booking and recovery action. Distinguish mechanical faults from commercial waiting time because the remedies differ. Use the actual hire agreement to decide whether standby is chargeable; never assume that being ready automatically creates an entitlement to payment.

Worked example or decision test

For illustration, five lost paid days at eight hours and AUD60 contribution per hour remove AUD2,400 of expected contribution before repair costs. This is a sensitivity example, not an industry downtime average. Test several durations and compare the results with available cash reserves.

The records to keep

Link the machine service schedule to bookings and supplier lead times. Record defects reported, competent assessment, repair completion and any release conditions. Client-required inspection evidence should match the equipment identifier; a generic maintenance folder can be difficult to use when several machines are working.

A useful next step

A useful monthly review asks whether a recurring fault, transport arrangement or booking practice is causing avoidable lost time. Good documentation does not prevent every breakdown, but it helps identify the cause, communicate honestly with customers and avoid repeatedly mobilising plant before the necessary records are ready.

Before using this approach, write down the particular job, the person who will confirm the information, the source files available and the question still unresolved. Review the result against the current agreement and official guidance. Keep estimates clearly labelled and preserve original evidence so another reviewer can follow how the decision was reached. Where specialist judgement is needed, give the adviser the complete facts rather than an isolated spreadsheet total or an edited excerpt.

Owner review

Use the downtime review to challenge the reserve assumption in the pricing model. If repeated transport delays are the main cause, buying spare parts will not solve the underlying problem. If servicing is being postponed to preserve bookings, discuss the operating plan with the responsible maintenance provider rather than treating availability as a purely administrative target.