A subcontractor can avoid a last-minute scramble by translating the contract deliverables into a live register at mobilisation. Begin with the client’s actual schedule, specification and approved inspection plan. Record each deliverable, package, location, owner, due date, required format and review route. During delivery, link every original file to the relevant line and note its revision and status.
Review the register weekly with the people who produce the records. Separate “not received” from “received but unclear” and “submitted, awaiting review.” Give every gap an owner and next action. Preserve superseded files and submission history; do not overwrite evidence to make the folder appear complete.
At handover, check naming, readability, traceability and the client’s folder convention. Ask the authorised reviewer to confirm technical acceptance. QBCC guidance lists examples of handover material, but the applicable scope depends on the contract and project. Growva can organise and index records; it cannot certify technical compliance or issue missing evidence.