An electrical subcontractor’s turnover pack should let the recipient connect the work package to its authentic drawings, records and equipment information. The required contents depend on the contract, work performed and applicable requirements identified by qualified people. This guide concerns collation and navigation, not electrical testing instructions or certification.

Start with the package boundary

Agree which systems, circuits, equipment and locations the pack covers. Use the identifiers in the project’s approved schedules and drawings. Record any exclusions or interfaces with other contractors so a reviewer does not mistake one trade’s pack for the complete project record.

Build the deliverables list with the electrical package owner. Possible headings to confirm include current drawings, inspection records, test files, certificates supplied by the responsible issuer, equipment literature, asset schedules, warranties and outstanding actions.

Connect each record to the work

A register can capture document ID, revision or date, circuit/equipment reference, location, source file, issuer, review status and open query. Use links to original files rather than manually retyping results into a summary that might later be mistaken for the test record.

If a certificate covers several items, record the stated extent and its source reference. If the scope is unclear, flag the question for the authorised electrical reviewer; do not infer coverage from a nearby file or similar equipment name.

Reconcile the common interfaces

An illustrative check is tracing one distribution board from the equipment schedule to its drawing, inspection record, relevant test evidence and supplied manual. If tags vary between files, record both labels and ask the package owner to confirm the relationship.

Also check interfaces that often span teams: incoming supplies, controls connections, vendor equipment and client-provided assets. The document list should state whose record is expected and which reviewer confirms it.

Prepare the submission without changing evidence

Preserve signatures, timestamps and source-file identity. Keep corrected issues and responses traceable. Do not recreate a missing test sheet, add a signature or relabel a record to cover another circuit. Authentic missing evidence must return to its responsible issuer.

Before issue, test links and check the index against the agreed deliverables. Provide a clear open-action list with owners and due dates. A documentation service may organise the material, while licensed work, technical interpretation and acceptance remain with the appropriately authorised people.